Final Permits

 

A. HOW TO APPLY FOR CERTIFICATE OF OCCUPANCY (also applicable to Certificates of Use and to Operate / not applicable to applications under the GREEN BUILDING ORDINANCE)

FOR ON-TIME RELEASE OF YOUR NEEDED PERMITS (12 days after application submission), MAKE SURE THAT ALL DOCUMENTS IN YOUR CHECKLIST ARE CORRECTLY PREPARED AND COMPLETE.

Follow all steps on 'HOW TO APPLY FOR BUILDING PERMIT'.

Proceed with the steps on 'HOW TO FOLLOW UP...' except that you can follow up after 7 working days.

Proceed with the steps on 'HOW TO GET YOUR RELEASED PERMIT AND APPROVED PLANS' except that "presentation of the tax declaration of the improvement is a condition for the release of the Certificate of Occupancy" (per Executive Order No. 17 Series of 2011).

B. HOW TO APPLY FOR CERTIFICATE OF FINAL ELECTRICAL INSPECTION (C.F.E.I. for Certificate of Occupancy, except for applications under the GREEN BUILDING ORDINANCE)

Proceed with the steps on 'HOW TO APPLY FOR BUILDING PERMIT'.

Proceed with the steps on 'HOW TO FOLLOW UP THE STATUS OF YOUR CERTIFICATE OF ELECTRICAL INSPECTION'.

Proceed with the steps on 'HOW TO GET YOUR RELEASED PERMIT AND APRROVED PLANS'.